Non-preemptive Shortest Job First
Example:
Process: p1 p2 p3 p4
Arrival time: 0 2 4 5
Burst time: 7 4 1 4
Schedule:
16
P1
8
7
12
P2
P3
P4
Waiting time: 0 6 3 7
Average waiting time: 4.